Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,464,908
Community Members
 
Community Events
176
Community Groups

Committed Tickets in a Sprint.

I have been analysing the committed Throughput of teams to assess the effectiveness of the planning they do.  This data has been useful for showing teams how much they over commit and start conversations about how to change the way they work and break work down to become more effective. 

The current way I am doing this is by counting the tickets in the sprint report without an '*' as these would've been added after the sprint start.   

I would like to get to a more automated way by exporting in to Excel/Google sheets and looking for a field or identifier that shows it was a committed ticket, not one added during the sprint.

I have looked in to EazyBi, exporting to google sheets and the current sprint reports.  The issue is that it does show the Committed but then for the done there is no separation between committed or added during the sprint.

There must be something that enables Jira to know the difference for the sprint report, but is it available for analysis elsewhere?

1 answer

0 votes

Hi, 

In eazyBI, there are new metrics related to completed of committed work.

You may see them used in a sample report: Story points commitment completion 

 

Best,

Ilze, support@eazybi.com 