Changing the value of "Working hours per day" from 8 to 12 and trying to specify a number of hours greater than 8 in the task results in the error message "9h exceeds daily limit of 8h". How and where is it managed?

1 answer

1 vote
Paloma Fondon Araujo
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 15, 2021

Hi @Andrius Kačionas 

Check the configuration of the hours per day in Jira's time tracking configuration and if necessary modify the values as follows: "Settings" --> Issues --> Issue Features and select Time Tracking:

Time tracking configure.PNG

I hope it helps,
Regards

Andrius Kačionas June 18, 2021

Hi,

All this is known. The problem with this is that the hours you enter here have no effect - when you try to log more than 8 hours, you always get an error message that 8 hours are exceeded, even though a 12-hour workday has been set.