You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi,
If you have for example 6 statuses for your workflow and and 1 of them is in the category = Done it is this category that allows you do close a sprint cleanly by having all issues in a status of this category. I think this is correct.
If this is true: can you create multiple statuses that are of category done and as long as the issues are in a different statuses but of the done category it will allow you to close the sprint without asking to move any issue to another sprint or backlog. This is how releases work, hoping sprints work the same way.
thank you
Not really.
when a sprint is closed, it considers all issues in the rightmost column to be done. Now, you should always make sure that only issues with a statuscategory of Done exist in the rightmost column. Otherwise it’ll create problems for you.
you can have more than one status in the right most column, and all of those will be considered done with the Sprint closes.
Yep, the "done" status category, resolution, and even status are all irrelevant. An issue is only done when it is in the last column on the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.