Estimated hours would be helpful during Sprint Planning and when dragging issues into a Sprint. Having that info at the summary level as well as at the Sprint total level (similar to the way total number of issues is currently displayed) would be most helpful. Is this something that can be configured?
Thanks Josh. I am assuming when you ask if Time my estimation statistic, that this is a setting at the project level that is needed. If that is true then no it is not currently set. I will review the link to further understand how to do so.
Regards,
Marc
Hi Marc,
Is time your estimation statistic for your sprint board?
Once it is, you will see the time estimate in the bubble on the far right side of the issue card.
More info on how to configure that is here: https://support.atlassian.com/jira-software-cloud/docs/configure-estimation-and-tracking/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.