Hi @Nico F_A_ -- Welcome to the Atlassian Community!
I am unclear what the speed report is. Do you mean the Velocity Chart:
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/
If so, the answer is "no" as that report shows up to the last seven sprints.
Of note, looking further back in time/iteration count may not be helpful. Often things change such that looking at old velocity may not be helpful. Such changes could include: team capacity, mix of work items, team improvements in workflow, etc.
In addition, I believe there are suggestions to expand the range of sprints reported upon.
Best regards,
Bill
Thank you! What you say about past sprints becoming a little irrelevant in terms of Velocity Charts makes sense now that you explain it to me that way.
And yes, I was referring to the Velocity Chart. Sorry for using the wrong term.