Can I view more than 7 sprints in a speed report?

Nico F_A_ August 11, 2020

Is it posible to generate reports with the bar graphs showing more than the last 7 sprints that were completed?

1 answer

1 accepted

0 votes
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 11, 2020

Hi @Nico F_A_  -- Welcome to the Atlassian Community!

I am unclear what the speed report is.  Do you mean the Velocity Chart:

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/

If so, the answer is "no" as that report shows up to the last seven sprints. 

Of note, looking further back in time/iteration count may not be helpful.  Often things change such that looking at old velocity may not be helpful.  Such changes could include: team capacity, mix of work items, team improvements in workflow, etc.

In addition, I believe there are suggestions to expand the range of sprints reported upon.

 

Best regards,

Bill

Nico F_A_ August 11, 2020

Thank you! What you say about past sprints becoming a little irrelevant in terms of Velocity Charts makes sense now that you explain it to me that way.

And yes, I was referring to the Velocity Chart. Sorry for using the wrong term.

Like Bill Sheboy likes this