Can I re-order sprints in the backlog view?

Justin Grant May 4, 2015

Our team uses the same board to track multiple ongoing sprints at the same time. Can I rearrange sprints on the board like I can do with releases?

2 answers

1 accepted

0 votes
Answer accepted
Justin Grant May 4, 2015

Figured it out. There's a "Move Sprint Up" option in the three-dot context menu on the right side of each sprint's header.

It's counter-intuitive that, despite the drag cursor shown when you hover over a collapsed sprint header, drag-n-drop doesn't work to move sprints up and down. Sigh. 

0 votes
CJ January 16, 2019

Hi Justin,

If you're still keen on this, there's a feature request to drag and drop sprints if you'd like to vote for it:

* Jira Cloud: https://jira.atlassian.com/browse/JRACLOUD-64086

* Jira Server: https://jira.atlassian.com/browse/JRASERVER-64086