I have a project with 3 Boards, 1 Kanban Board and 2 Scrum Boards.
I already have a separate backlog for the Kanban board, however, my scrum boards are sharing the same backlog, I need to have separate backlogs for each scrum board. Is that possible?
Yes, you can change the backlog for each board by changing the filter for each board. For example, in my project I have a board for one team with a filter that searches for that team and another board for another team that uses the filter where it specifies that particular team.
Each board will then only show those items assigned to that team.