Burndown chart

Rahul Aich [Nagra]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 17, 2013

Hi All

I am using the classic boards on greenhopper. and on clicking charts i only get to select the predefined charts i.e hour burndown chart. I want to view the chart in units of days in stead of hours.

Is it possible?

Rahul

1 answer

1 accepted

1 vote
Answer accepted
Alex
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 17, 2013

Hi Rahul,

You can configure JIRA Time Tracking (which defaults to minutes) to days which should enable you to configure your GreenHopper Board to the day time series.

See here for configuring time tracking in JIRA: https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking

See here for configuring your GreenHopper Board:

https://confluence.atlassian.com/display/GH/Configuring+Estimation+and+Tracking

I did find this open bug relating to display time series in days not hours for the burndown chart. Apparently, you can change the time series in JIRA to days but it is not reflected in the Burndown Report even though the time series on the graph changes to days (according to this ticket).

Please vote on the JIRA ticket if you'd like to see it resolved: https://jira.atlassian.com/browse/GHS-5447

Thanks,
Alex