Hi All

I am using the classic boards on greenhopper. and on clicking charts i only get to select the predefined charts i.e hour burndown chart. I want to view the chart in units of days in stead of hours.

Is it possible?

Rahul

1 answer

1 accepted

This widget could not be displayed.

Hi Rahul,

You can configure JIRA Time Tracking (which defaults to minutes) to days which should enable you to configure your GreenHopper Board to the day time series.

See here for configuring time tracking in JIRA: https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking

See here for configuring your GreenHopper Board:

https://confluence.atlassian.com/display/GH/Configuring+Estimation+and+Tracking

I did find this open bug relating to display time series in days not hours for the burndown chart. Apparently, you can change the time series in JIRA to days but it is not reflected in the Burndown Report even though the time series on the graph changes to days (according to this ticket).

Please vote on the JIRA ticket if you'd like to see it resolved: https://jira.atlassian.com/browse/GHS-5447

Thanks,
Alex

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,483 views 10 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you