Hello All,

Burndown chart is not updating when changing the start time of Sprint

I have started the sprint on 5th Dec for 2 weeks of duration which ends on 16th Dec.

Query is: I have started the sprint, after that team updated couple of hours, then to display the burndown accurate, i have adjusted the sprint start time to current tool time, but chart was not updated.

Same kind of update I use to do in old JIRA version, it was worked fine. but seeing this issue on latest version update. 

Please let me know if any has suggestions.

 

thanks

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 6, 2022

Welcome to the Atlassian Community!

Do not adjust the sprint start time, it's misrepresenting what you are doing.  Leave it in place, and accept that your people adjusting in-sprint estimates are recording scope creep in the sprint.