Burndown chart not burning down

We've just started a new sprint and have decided that we want to use Time Tracking based on Remaining Estimate and Time Spent.


The sprint was created, issues added to the sprint with original time estimates and it was started yesterday. The developers have been logging their time and updating the remaining time estimate as they go along and setting it to 0 once they have completed the issue. The issue is then moved to the Close column on the board. 

The burndown chart is however not representing this information. I am just getting two horizontal lines (one red and one green). What have I set up incorrectly? 

This is a snippet of the actual burn down chart

image2015-6-16 11:46:37.png 

4 answers

0 vote
Brian Cruz Atlassian Team Jun 15, 2015

Hi Fayez,

This could be due to a multitude of reasons. I would recommend taking a look at the documentation for the Burndown Chart and see why it's not burning down the way you'd expect it to. Looking at the documentation you should see information about the burndown below the chart. Is this not coming up? I'd open up a cloud support ticket and have them take a look at the configuration.

Hi Brian,
Thanks for the quick response. Here is another snip of the info from below the chart. The issue seems to be that when time is logged against the issue (and the remaining estimate is changed), it is not appearing in this table. When I manually modified the remaining estimate, the change appeared (last lines). If it is of any help, we have the tempo plugin installed and we use that for our time tracking as well

image2015-6-16 13:44:47.png 

What have you configured for estimation statistic and time tracking for this board?

This issue seems to have fixed itself. The time that was not appearing was 'magically' recorded later that day at midnight (not manually). Now, any time logged is appearing immediately.

Estimate Statistic was Original Estimate and Time Tracking was Time Spent & Remaining Time 

Did you check the "Refresh Interval" for the gadget?  I typically set gadgets with frequent or dynamic data changes to a shorter interval, and data points that rarely change to a longer interval (or never).

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,243 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you