Burndown chart - Status "not closed"

Peter Karam August 21, 2022

We have a scenario where issues that are completed in a sprint need to be kept at "Ready for UAT" status , and not to be closed. That being said, we are not able to make use of Burndown chart.

Is there a way to configure the burndown chart to depend on a status different from "Closed/Done" (i.e. "Ready for UAT") ?

or any other advice?

1 answer

1 vote
Rik de Valk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 21, 2022

Hi @Peter Karam ,

Yes that is possible. The Scrum board will consider and status that is mapped to the last column in your Board as done. 

So you can map Ready for UAT to the last column and your burn down will act accordingly.

Have a nice day! 