Burndown chart - Status "not closed"

We have a scenario where issues that are completed in a sprint need to be kept at "Ready for UAT" status , and not to be closed. That being said, we are not able to make use of Burndown chart.

Is there a way to configure the burndown chart to depend on a status different from "Closed/Done" (i.e. "Ready for UAT") ?

or any other advice?

1 answer

1 vote
Rik de Valk Community Leader Aug 21, 2022

Hi @Peter Karam ,

Yes that is possible. The Scrum board will consider and status that is mapped to the last column in your Board as done. 

So you can map Ready for UAT to the last column and your burn down will act accordingly.

Have a nice day! 

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira Software

An update on Jira Software customer feedback – June 2022

Hello Atlassian Community! Feedback from customers like you has helped us shape and improve Jira Software. As Head of Product, Jira Software, I wanted to take this opportunity to share an update on...

4,964 views 18 31
Read article

Atlassian Community Events