Burn points on a different column that is not the last one?

aduarte June 4, 2020

We have two final columns... "Ready for demo" and " Done". I want to burn the points on Ready for Demo because Done is used on the demo meeting at the end of the sprint.

 

Is there a way to burn points on a different column that is not the last one?

1 answer

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 8, 2020

Hello @aduarte

Thank you for reaching out.

Unfortunately, Jira boards do not support multiple columns with the done status category, so it is not possible to configure multiple columns where the issue would be considered complete.

We have the following feature request to implement this option:

In Configure Board, allow multiple "Not Started" (Blue) and "Done" (Green) columns 

Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.

Additionally to that, can you please let us know why do you need the issue to be considered completed in a different column exactly?

As a possible workaround, you can map the two final statuses in the same final column, using a different field (As resolution or Labels) to differentiate them.

Let us know if you have any questions.