Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Bunrdown report not showing appropriate curves

Gustavo
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Oct 10, 2023

The curves don´t show the expected results

burndown.JPG

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 11, 2023

Welcome to the Atlassian Community!

You have not explained what you are expecting, so we can't really start to look at why there might be a problem.

However, we can explain what you are seeing in this chart.  It looks like you started a sprint with no issues with any sprint estimates on them, then towards the end of the sprint, you either added new issues with estimates into the sprint, or you put sprint estimates on some issues in the sprint.