You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi.
I am using Jira + BigPicture.
When I create a dependency (in BigPicture) between two epics in an end-to-start relationship, the second / downstream epic does not appear to get auto-rescheduled to begin after the first / upstream epic.
Is there a reason why the auto-scheduling is not happening for the downstream epic?
When I link a task from the upstream epic to a task in the downstream epic, the auto-schedule does occur.
Thanks for your help, folks.
Regards, Andy