You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello all,
I am trying to create an automation rule that will periodically create a maintenance task for me with a series of subtasks.
I have a rule that creates a scheduled task for me. This works. But I can't get the subtasks to be created in the same process. So my question is, can I create a task and subtasks scheduled by date in an automation at all or do I have to create two tasks here?
Thanks in advance for the support!
Hi @cDemmerle
This can be achieved using the Branch rule / related issues option in the rule:
Result on 1 execution:
Hopefully this answers your questions,
Regards,
David
Thx Works great and was soo simple i haven`t seen that Option when playing around :-D .
Thx again and have a nice week!