Hello all,
I am trying to create an automation rule that will periodically create a maintenance task for me with a series of subtasks.
I have a rule that creates a scheduled task for me. This works. But I can't get the subtasks to be created in the same process. So my question is, can I create a task and subtasks scheduled by date in an automation at all or do I have to create two tasks here?
Thanks in advance for the support!
Hi @cDemmerle
This can be achieved using the Branch rule / related issues option in the rule:
Result on 1 execution:
Hopefully this answers your questions,
Regards,
David
Thx Works great and was soo simple i haven`t seen that Option when playing around :-D .