rob March 12, 2014

Our Sprint Health Gadgets don't seem to include the time we've estimated on subtasks in the health. Is there a workaround for that? I'd sure like to see that work included.

1 answer

1 accepted

1 vote
Answer accepted
Anna Cardino
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 21, 2014

Hi Robweidmann,

This seems to be an expected behaviour as stated in http://blogs.atlassian.com/2012/09/agile-qa-greenhopper-time-estimates-with-sub-tasks/.

However, I came across to this ticket describing the functionality that you need; GHS-9167.

Kindly to the following on the ticket to increase it's popularity and get more attention to Atlassian developers:

* Vote, so that it will receive more attention

* Watch it, so that you will receive any and all updates

* Comment, and give your opinion on the matter

Hope it helps.
Regards,
Monique