Are subtasks included in sprint health gadget calculation?

Our Sprint Health Gadgets don't seem to include the time we've estimated on subtasks in the health. Is there a workaround for that? I'd sure like to see that work included.

1 answer

1 accepted

1 vote
Anna Cardino Atlassian Team May 21, 2014

Hi Robweidmann,

This seems to be an expected behaviour as stated in http://blogs.atlassian.com/2012/09/agile-qa-greenhopper-time-estimates-with-sub-tasks/.

However, I came across to this ticket describing the functionality that you need; GHS-9167.

Kindly to the following on the ticket to increase it's popularity and get more attention to Atlassian developers:

* Vote, so that it will receive more attention

* Watch it, so that you will receive any and all updates

* Comment, and give your opinion on the matter

Hope it helps.
Regards,
Monique

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

13,173 views 15 13
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you