Agile: moving a user story from sprint to backlog

I want to move a user story from an open sprint back to the backlog, but it doesn't work - it stays in the sprint.

The project admin and I (JIRA Admin) tried it both, but it doesn't work.

Any ideas?

3 answers

1 accepted

This widget could not be displayed.

Nope, didn't work. It worked for me now as follows:

1. right click on user story and "Remove from sprint"

2. It is sent to the next sprint

3. From there: right click (or drag/drop) and "Send to backlog"

br,

Werner

I didn't think about how having multiple planned sprints would impact that problem, good solution.

Thanks anyways Peter! The discussion helped me to figure it out.

Hi.. I am using Atlassian JIRA v5.0.1(bit old), is it possible to move a story from active sprint to backlog or another upcoming sprint?

This widget could not be displayed.

Hi Werner,

Which version of Jira and Jira Agile are you using?

Is it an active sprint or just a planned sprint?

Did you get an error message?

Best regards,

Peter

Hi Peter!

Here are the answers to your questions:

JIRA 5.2.6

JIRA Agile 6.2.5.1

It is an active sprint and there are no error messages, it just doesn't work.

Best regards,

Werner

Hi Werner,

I just tried it (drap it from the active sprint in the plan view to the product backlog) and that seems to work, but only for issues that are still in the first column of my scrum board.

Did you already work on the issue that you want to remove from the sprint?

Can't you just simply close the sprint with the issue still in it? It will be automatically moved back to the top of the product backlog.

Best regards,

Peter

This widget could not be displayed.

It is in the first column and the work on it hasn't started right now.

The problem is that there are many issues in that sprint, so we don't want to close it.

Normally, when I move over the user story in the plan mode and make a right-mouse-click, i get "Send to top/bottom of backlog", but it seems that this works for future sprints (=not started) only.

Did you try to just drap it out of your sprint onto the product backlog,

That works for me.

Best regards,

Peter

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

1,069 views 5 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you