Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,340
Community Members
 
Community Events
176
Community Groups

Advanced Roadmaps - Sprints along timeline

In the training and in the documentation it states that sprints can be placed along the timeline as "Projected Sprints" to help with capacity planning and tracking. 

projected sprints.png

 

As described with this article: 

https://support.atlassian.com/jira-software-cloud/docs/monitor-capacity-on-your-advanced-roadmaps-timeline/

 

The solution is to groups by Sprints as described in this article: 

https://support.atlassian.com/jira-software-cloud/docs/enable-capacity-planning-in-advanced-roadmaps/

 

Screen Shot 2021-12-20 at 5.17.31 PM.png

 

As seen above, I have done this and have assigned a team and yet the sprints are listed in the left instead of along the timeline as desired. 

 

Screen Shot 2021-12-20 at 5.19.53 PM.png

 

I've clicked all the settings and tried in every way I can think of to resolve this and yet I can't get it to work as desired.... Any ideas?

1 answer

1 accepted

1 vote
Answer accepted

Hi @Akira Mitchell ,

 

It looks like we may need to update our docs... the view settings you need for this view are group by team (not sprint), with the show capacity box checked.

 

Hope this helps, and i'll make sure we get our docs updated!

 

Emma

Thank you @Emma Ysebaert Yes this did resolve the issue. Unfortunately it means that everything is included from initiative to subtask without discrimination but I believe this is a start date issue on our end. 

 

Thanks again for your help! 

 

Screen Shot 2021-12-21 at 10.46.03 AM.pngScreen Shot 2021-12-21 at 10.48.17 AM.png

I have jumped through hoops and looked for article to get the sprint dates to follow the timeline - it's not working.   And very ridiculous that it takes 1500 plus people to ask for this and it doesn't exist and is basic on the non premium version!