Advanced Roadmaps - Auto-scheduling with fixed-length tasks

samson January 11, 2022

Hi, 

I'm trying out advanced roadmaps to auto-schedule a complex project with many major fixed time interval tasks (e.g. vendor takes 2 weeks to finish job whenever it's sent out, job needs to run for 3 days to complete, etc) which take no actual team-hours. Of course many tasks that do cost team-hours depend on these intervals. Is there any way to reasonably do this in Advanced Roadmaps? Only way I'm thinking of right now is to create a dummy team for each task and assign story points, but that might require an arbitrarily large number of teams depending on how many overlapping tasks there are.

Thanks!

0 answers

Suggest an answer

Log in or Sign up to answer