Add story to a closed sprint

Chris Tooley October 24, 2012

I have had some occurrences of Scrum Masters closing a sprint (from the Rapid Board) after someone has "accidentally" removed a closed Story. Is there a way to put that story back in the closed sprint via the UI or database?

1 answer

1 accepted

0 votes
Answer accepted
Annicka Rosengren October 25, 2012

One way is to temporary add the Sprint field to the edit screen, and add the id of the sprint in the sprint field for the missing story. But it will not be included in the sprint report as that already has been generated. But it included if you search on that sprint in the issue navigator

Chris Tooley October 31, 2012

Unfortunately this seems to be the only way to work it out. Disappointing.

Suggest an answer

Log in or Sign up to answer