Add story to a closed sprint

I have had some occurrences of Scrum Masters closing a sprint (from the Rapid Board) after someone has "accidentally" removed a closed Story. Is there a way to put that story back in the closed sprint via the UI or database?

1 answer

1 accepted

0 votes
Accepted answer

One way is to temporary add the Sprint field to the edit screen, and add the id of the sprint in the sprint field for the missing story. But it will not be included in the sprint report as that already has been generated. But it included if you search on that sprint in the issue navigator

Unfortunately this seems to be the only way to work it out. Disappointing.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 29, 2019 in Jira Software

Transforming Jira Software projects for general project management purposes

...It's true that there are projects in Jira; but they are merely a way to cut off issues, to tell them apart from other sections of work and to apply rules that are specific to that team (the schemes)....

206 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you