Hi, we are working on a scrumban project, using a Kanban board but organizaing our deliveries by sprints. We have created a project but we can't start sprints, so I imagine that was created in the past as a Kanban project. My doubt is: if I want to start using sprint, do I have to create a new Scrum board and assign it with the existing project? How it's going to change the visualization? We don't want to loose the information. Can we make a roll-back if we don't like it? Many thanks in advance!
Hi @Elisabet Griera welcome to the Atlassian Community!
Depending on your definition of scrumban:
You can create both a Kanban and a Scrum Board for your project. Nothing will break and you can decide which suits best.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey, If you want to start using sprints - yes you do need a scrum board, but you can create it on the same basis as existing Kanban project
You can do it by going to search > see all boards > create a new board
Choose Scrum board and then choose either create from existing project and choose from existing filter and choose the same filter you use for your kanban board. Then choose for the board to be visible in a project you want it to be in :) [ It will only allow to show it in Scrum projects - but the important thing is the issues are the same
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.