2 teams using 1 backlog using Jira Agile

Christiaan Hentzen November 17, 2013

Ls,

Is it possible to use with 2 teams one backlog in Jira Agile?

I cannot start 2 sprints at the same moment.

regards

Christiaan

2 answers

1 accepted

0 votes
Answer accepted
Christian Czaia _Decadis AG_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 17, 2013

Even though I'm not really sure what you want to accomplish (I mean you could plan in one backlog, and use a different board for each team / using a team marker, custom field....) you can enable parallel sprints:

https://confluence.atlassian.com/display/AGILE/JIRA+Agile+Labs#JIRAAgileLabs-ParallelSprints

Cheers

Christian

0 votes
Christiaan Hentzen November 18, 2013

Thank you very much it worked perfectly!

Suggest an answer

Log in or Sign up to answer