I was wondering if others are seeing this issue.
I have Sprint 1 with a 2 point story and a 5 point story starting out. The sprint finishes with only the 2 point story getting finished. I close the sprint moving the 5 point story back to the back log. I run the velocity report and it shows Sprint 1 Commitment of 7 points and completed 2 points. Which is exactly what I would expect. Now I repoint the 5 point story to 3 points and rerun the velocity report. It now shows Sprint 1 Commitment of 2 points and completed 2 points. So it looks like we delivered what we comitted to. This just does not seem right to me, we committed to 7 points and failed to deliver 5 points. Are other seeing this issue?
Thanks for trying. It happens every time for me. May I ask what version you are running.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bryan,
I tried to reproduce this issue on our server version but could not reproduce it. The velocity report worked as expected and kept the committed and completed numbers the same.
Regards,
Bill