I have created 4 subtask of 10 hrs under one main task. These 40hrs are not gettng shown under burndown chart.
Do i have to enter sum of subtask under main task estimations?
Then how work logged under subtask get deducted from main task?
Burndown is not looking correct if mail task hours are not entered.
Burn-down is something that measures progress on delivery of what you committed to doing during a sprint. In scrum, you commit to doing stories, sub-tasks are not mentioned by it. When you use them in scrum, they're a tool for the team to help break up stories into pieces for various reasons (several developers so different assignees, different sub-systems, types of work, and so-on). The sub-tasks are completely irrelevant to whether a commitment is met. You burn-down on the story, not bits of it.
So, the short story is that you do not do (scrum/burn-down) estimates on sub-tasks.
There's no roll-ing up or other accumulation schemes implemented in Jira (and most of the ones people decide to design and implement don't work either)
If you want to estimate in hours, and reference sub-tasks, then, without any code, you have three options:
All of these will require you to manually copy hours between the two types of field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For both 1 and 2, create a custom field for "hours", making it a simple number field
For approach 1:
For approach 2
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for reply @Nic Brough -Adaptavist- . Will you please help me how can I implement point 1 or 2 in Jira Cloud.?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.