JIRA summation of story points / story point estimates per release

Eshwar Chand Ranga February 21, 2019

I am trying to sum the story point estimates per release and generate a report in JIRA, but i am not able to do so. Can anyone have idea on how to get such report ?

 

Exmaple: 

Release 1 - story point estimates = 1050 Hrs

Release 2 - story point estimates = 2500 Hrs

1 answer

0 votes
Kevin Bui
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 21, 2019

Hi @Eshwar Chand Ranga - I might be misunderstanding you, but it sounds like the Release Burndown chart in Jira will give you the information you want?

https://confluence.atlassian.com/jirasoftwarecloud/release-burndown-777002702.html