Different total scope between burnup and burndown

I am comparing the burndown and the burnup charts for our current sprint.

When I examine our sprint board, we have 116 points in the sprint today, and we have 32 points remaining to complete

The burndown chart is showing that our peak total scope was 116, and shows 32 points remaining.

The burnup chart is showing 140 points scope, and 87pts completed. We had some tickets erroneously added to our sprint, but we since removed those.

I would assume that if we accidentally added 24 points, but then removed those 24 points, they would be removed from the burnup graph?

Am I doing something wrong? Am I misunderstanding how this works? Is this a bug?

0 comments

Comment

Log in or Sign up to comment
TAGS
Community showcase
Published in Trello

🏊‍♀️ Atlympic Event: Trello

Hello Community!  Quick disclaimer: We are running a contest on Community (The Atlympics!) from July 23rd - August 8th of 2021. If you are interested in participating in this contest (prizes! ...

153 views 2 12
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you