This has worked in the past. On my BigGantt gantt chart, the task is showing visually as happening on Oct 11 (Sunday), its actual date is Oct 12. When I hover on the gantt task it says 'oct 12'. See snapshot.
Hello @Robin Raben
We are aware of this bug. Our Dev Team has completed works on fixing it, and now it's waiting for the release in BP 8.0.4 version. The release is planned for next week (third week of October).
Best regards,
Anna
SoftwarePlant Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.