BigPicture gantt chart visual shows a day earlier than actual date of a task

Robin Raben October 9, 2020

This has worked in the past. On my BigGantt gantt chart, the task is showing visually as happening on Oct 11 (Sunday), its actual date is Oct 12. When I hover on the gantt task it says 'oct 12'. See snapshot.

ganttissue.png

1 answer

0 votes
Anna-BigPicture
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
October 16, 2020

Hello @Robin Raben

We are aware of this bug. Our Dev Team has completed works on fixing it, and now it's waiting for the release in BP 8.0.4 version. The release is planned for next week (third week of October). 

Best regards,
Anna
SoftwarePlant Support

Robin Raben October 16, 2020

great news! thank you!