JIRA reports without time tracking

Hello everybody, 

We have a local JIRA instance. We have a number of projects we are managing through JIRA. 

I am a project manager and want to get more detailed reports on how tickets are doing. I do have a dashboard setup which is good to view current progress, but I'm not sure if it is the best for historical and high-level data. 

The big issue is that we do not use time-tracking. We also do not use any variation of AGILE. I had tried to introduce it and it didn't stick at all. We do have a relatively solid workflow as we track the ticket progression from creation to creative, creative review, dev, dev review, client, client review, etc. 

I was wondering if there was a way that I could simulate timetracking by creating a start/stop progress field and then get the time based on how long it spent in the 'start progress' field. I'm not sure if this could work. 

I want to know what are the best and most meaningful reports that I can create given the data that I have. Most of the ones I see are related to time tracking. 

Any information would be very helpful!

1 answer

1 accepted

0 votes
Jack Brickey Community Champion Dec 06, 2017

@Aaz,

You could certainly gather 'time spent in status' using plugins but IMO this would be horrible data to attempt to infer anything valuable. By valuable I mean actionable. If the dev team doesn't log time and do so in a dependable way then there isn't much you can do to assess velocity, etc. 

 

warning...the rest of this response is opinion based upon experience.

 

As a project manager you need to either accept the way the team works and try to slowly invoke change or drive Agile from the top down if the bottom up isn't working. My experience is that you need someone from w/in the dev team to champion this, either a key respected team lead or the manager/director. Maybe you can get the team to start by using the estimation field but not logging time and or use the Due Date. If that is successful then introduce logging at a later time. One of the key selling points to development is that time logging helps define what the team 'can' do (velocity) so that it can be fed back into the planning of the next sprint/itteration/release vs. overbooking the team. In other words Velocity is a tool that Dev can use to their advantage.

@Jack Brickey Unfortuantely, we are a small company and I've already talked to the team top-down and bottom-up and logging isn't happening. 

Can you please tell me what these plugin options are for gathering time spent in status. Or if there is other useful data?

Jack Brickey Community Champion Dec 07, 2017

you can search in the Marketplace and here is what I found w/ quick search.

Thank you Jack. 

 

Seems like I have a lot of thinking to do on how to optimize our workflow. 

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

241 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot