Jira Tempo - Plan Time

Michal Walt June 30, 2020

hi

I am using Jira Tempo Plan Time & Worked Time, so I can monitor actual vs. planned.

I would like to plan time also for my team members, but could not find a way to do it, as this is done only in the "Calendar" view and not the "Timesheet" view of Tempo.

any idea?

thanks in advance

Michal

1 answer

1 accepted

0 votes
Answer accepted
Susanne Götz _Tempo_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 30, 2020

Hi @Michal Walt 

In Tempo Timesheets, Calendar view, users can only create plans for themselves.

Planning time for other users is done in the Resource Planning view of Tempo Planner (https://tempo-io.atlassian.net/wiki/spaces/THC/pages/310509942/Resource+Planning+-+Tempo+Server)
or the Issue view (https://tempo-io.atlassian.net/wiki/spaces/THC/pages/494600994/Planning+in+the+Jira+Issue+View+-+Tempo+Planner+for+Server).

Team leads have the permission to plan for their team members by default. Other users need the "Manage team plans" permission to do this (https://tempo-io.atlassian.net/wiki/spaces/THC/pages/386302535/Planner+Permissions+-+Tempo+Server).

Best regards,
Susanne Götz
Tempo team