If i reuse my story from "Previous Sprint"...My time tracking field should start from "Zero" too

Deepan V.R September 13, 2019

I have created a sprint 1..Estimated 5 hrs..and burnt 3 hrs...

Then i am pushing the same story to next sprint...Can my Time tracking field can start from "Zero"...

Asking this because..Time tracking's estimates....is prelogged when i push to next sprint too..

 

Need your help on thisCapture.PNG

1 answer

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 16, 2019

Hello Deepan,

Thank you for reaching out.

It is the expected behavior to keep the Time tracking field of the issue even after the current Sprint is closed.

Currently, you are able to manually delete work logs and set the Original/Remaining Estimate to 0h, however, there is no way to bulk delete work logs.

In fact, we think that the bulk edit of Time Tracking would be useful functionality, so we created a feature request to get it implemented:

Bulk Edit: Time Tracking Estimates

Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.

As a workaround, you can bulk edit issues using the JIRA REST API.

Let me know if you have any questions.