what does the error "resource limit violation" mean and how can I solve this issue?

I have been using Portfolio for a while and it's the first time I get this error.  I have my teams setup and I have all the necessary skills to complete the story.  I can build the plan but when I assign the team the row is pink and it won't allow me to assign the team.

I searched and couldn't find any information about this error.

 

1 answer

Not sure if this is an issue in Portfolio 2.0, but I have the fix for the legacy version

Drove me crazy all day and just figured it out.

 

Under: Plan > Configure > Planning > Scheduling

Scroll all the way down to: "Maximum resources"

Increase the number of resources to the maximum you want to have collaborating on them at the same time.

 

Good luck!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

375 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you