what does the error "resource limit violation" mean and how can I solve this issue?

I have been using Portfolio for a while and it's the first time I get this error.  I have my teams setup and I have all the necessary skills to complete the story.  I can build the plan but when I assign the team the row is pink and it won't allow me to assign the team.

I searched and couldn't find any information about this error.

 

1 answer

Not sure if this is an issue in Portfolio 2.0, but I have the fix for the legacy version

Drove me crazy all day and just figured it out.

 

Under: Plan > Configure > Planning > Scheduling

Scroll all the way down to: "Maximum resources"

Increase the number of resources to the maximum you want to have collaborating on them at the same time.

 

Good luck!

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,138 views 6 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot