issue closed date on subtask

Hi

I would like to show on the main issue when a subtask is closed. 

I know that in Advanced settings I can configure what columns to show on subtask, not sure what is he name of the column which will give me date when issue is closed.

Please let me know.

Abe

1 answer

Try using resolution date. It is the date when an issue was resolved. If you make filling resolution on this step - this is your solution.

If you want to get the of transition to state "Closed" you need to analise change history via script (need programming)

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

23 views 2 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you