how to start a sprint while having error message: "can be planned... "

Tyhnec March 27, 2016

This question is in reference to Atlassian Documentation: Starting a Sprint

i have this error: can be planned but not started until the completion of above active sprint. though all of the tasks are done.  

so i assume that i need to ask how do you define 'completion' of the sprint ? 

appreciate your time and help

 

thanks!

2 answers

1 accepted

2 votes
Answer accepted
Sten Sundelin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 28, 2016

In JIRA 6.4 with JIRA Agile 6.7.12, go to sprint board 'Active Sprints' view, you click on the down arrow by the sprint name and click on 'Complete Sprint...' button.

If you don't see it, you don't have the permissions to close the sprint.

Tyhnec March 28, 2016

thanks a lot

2 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 28, 2016

You have to formally end it (you don't need everything in "done" to do that, although it is the aim of the sprint!).  See https://confluence.atlassian.com/agile/jira-agile-user-s-guide/working-with-sprints/ending-a-sprint

Tyhnec March 28, 2016

thanks a lot

Suggest an answer