Hi
I'm new to this, but how can I remove/ hide Epics, user stories or tasks that arent needed?
Also how could i indicate that a task relates to a number of user stories/Epics?
Sorry Im an University Student and Im new to JIRA and Agile (about 4 weeks experience)
If you are talking about hiding the Epics, stories etc from the Agile board, you can do that with the help of the board query. Each board shows issues based on a filter and you can modify the filter to exclude issues you do not need.
Task - Story relation can be created using JIRA issue links.