I added multiple sub tasks under my story while create it. Later I have added more sub tasks. Now I have to either move up the sub tasks one by one in the order, which is painful. Is there a way to either drag and drop to change the order or give sub tasks custom number?
hi,
you can't change the id but I think you will find this answer useful:
https://answers.atlassian.com/questions/155275
you add a bookmark with the given code, go to the parent issue, click on the bookmark and drag&drop your subtasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.