i am using the time based tracking and confured my board to use the as original time estimate & Time Tracking to Remaining Estimate and Time Spent
I see below chart if i simulate a user entering the daily time consumed. why this chart is not showing the line as shown traditionally(either above or below the guideline). how does this chart tells that team is on track or not. i am not able to get any value.. is this a bug? i am using JIRA v6.4.11..
Sprint Burn down chart..
image2016-4-9 16:19:0.png
This is my Log. i started with 4+6h of total effort.
Date | Issue | Event Type | Event Detail | Inc. | Dec. | Sum | Inc. | Dec. | Remaining |
---|---|---|---|---|---|---|---|---|---|
11/Apr/16 12:05 PM | YNXMY-206 YNXMY-207 | Sprint start | - - | 0 | 4h 6h | 1d 2h | |||
12/Apr/16 12:53 PM | YNXMY-206 | Work logged | 2h logged, Remaining Time Estimate changed from 4h to 2h | 2h | 2h | 2h | 1d | ||
12/Apr/16 12:54 PM | YNXMY-207 | Work logged | 3h logged, Remaining Time Estimate changed from 6h to 3h | 3h | 5h | 3h | 5h | ||
13/Apr/16 12:55 PM | YNXMY-206 | Work logged | 2h logged, Remaining Time Estimate changed from 2h to 0 | 2h | 7h | 2h | 3h | ||
14/Apr/16 12:58 PM | YNXMY-207 | Work logged | 1h logged, Remaining Time Estimate changed from 3h to 2h | 1h | 1d | 1h | 2h | ||
14/Apr/16 12:59 PM | YNXMY-207 | Work logged | 2h 30m logged, Remaining Time Estimate changed from 2h to 0 | 2h 30m | 1d 2h 30m | 2h | 0 |
The chart matches what you've done as far as I can see. Could you explain what is missing/wrong a bit more for us?