I'm asking that silly question as I have started a sprint and 2 of the issues initially added are considered as "added after sprint started" even if that is not true... Anyone knows what is the logic behind in jira?

1 answer

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 18, 2019

Hello,

I believe you should compare the date, when the Sprint value was set for the issue, and the start date of the sprint.

You can find the date, the Sprint value was set, in the Issue History.

Javier Perez February 18, 2019

yeah it seems that the dates of start sprint are not well set up...

 

Really weird as I moved the stories to the sprint and then I click on start. I guess the start date in the sprint was not correct....