What are the best steps for upgrading from jira 3.13 to jira 7 ?

Hi everyone,

I need to upgrade from JIRA 3.13 for a large customer in Romania . I'm curently working on a test environment with Windows 2008 Server and MSSQL DB. What are the best intermediate versions for upgrade?

Thank you, Mihai

1 answer

1 accepted

1 vote
Answer accepted

It's very dependent on your testing, but I'd start with a plan for 3.13 -> 4.4 -> 5.2 -> 6.4 -> 7.0  (I'd try skipping the 5.2 version if possible, but the rest will probably bite you somewhere if you miss them)

Thanks for the reply . Did you have some other advices , maybe some tips&tricks for this large upgrade? smile

Not a lot beyond "read all the release notes", and "test it".  You're going to have issues with it somewhere, but there's not a huge amount of general advice I can give you that is beyond "common sense"

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

386 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you