Velocity Chart : shows no "completed" work?

meconlin November 12, 2016

For both our open and closed sprints our velocity chart shows no "completed" work.

Work is being completed and moved to the rightmost column in our boards configured columns.

What could cause this?

 

Screen Shot 2016-11-12 at 5.23.55 AM.png

 

2 answers

0 votes
Suresh Venkat November 23, 2020

We did project level reindexing and that solved our problem.

0 votes
Sam Hall
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 12, 2016

Hi Mark,

I got a similar issue after accidentally removing the rightmost column in my board configuration.

I'll try to show before and after using some screenshots to explain...

Before:

I had columns set up like this:

columns-before.jpg

... and velocity chart was looking fine for completed sprints:

velocity-chart-before.jpg

After:

I removed the 'Done' column. This resulted in the 'Done' issue status becoming unmapped...

columns-after.jpg

... which broke my velocity chart for Sprint 2:

velocity-chart-after.jpg

If I look at the Sprint Report for Sprint 2 after this, I see that it is now showing issues under the heading "Issues Removed From Sprint" (rather than as "Completed Issues").

This is because the 'Done' status (which these issues were in when the sprint was completed) is no longer mapped to show on the board.

If you haven't already, it would be worth checking if you have any unmapped statuses like this.

Failing that, this Atlassian Knowledge Base article might help you rule out some other reasons: https://confluence.atlassian.com/jirakb/issues-are-not-appearing-in-boards-779159013.html

Anyway, I hope my answer is helpful. 

Sam

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events