  • Typically, a user story may have mutlpile tasks & sub-tasks assoicated to it, of which the tasks & sub-tasks can be assigned to various versions or sprints, correct?

Typically, a user story may have mutlpile tasks & sub-tasks assoicated to it, of which the tasks & sub-tasks can be assigned to various versions or sprints, correct?

Ken Kinzer August 25, 2016
 

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 25, 2016

Not quite.

A user story may have multiple sub-tasks.  It may also be linked to other things such as tasks at the same level, Epics above it or even sub-tasks on other issues, but these links are informational, they do not mean that anything linked "belongs" to the story.

You can put a user story into a Sprint.  It takes its subtasks with it, but not linked issues. 

You can put a user story, and sub-tasks into any version or versions you need to.

Suggest an answer