Task cloning and time dependencies

Kara Sheil December 16, 2015

This question is in reference to Atlassian Documentation: Task management with JIRA

When cloning a task, and need time dependencies among the sub-tasks (ie sub-task 1 needs to start 2 months before sub-task 2, and sub-task 3 always starts two weeks after sub-task 2. Is there a way to set a start date for sub-task 1 and have the rest cascade out from there?

1 answer

0 votes
Steven F Behnke
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 16, 2015

Not automatically, no. This sounds like a customization, you'd like something that is totally out of JIRA's control. 

You could write an add-on. You could use the external API to achieve this with your own script.