Sum of Time Tracking for Project

I've created a simple project with multiple Epics, and multiple Stories linked under those Epics.

 

Each Story has a Time Tracking -> Remaining number of hours configured against it.

 

All I want to see is a sum of all the Remaining hours for all issues. I'm quite amazed this isn't on the Project Summary view. How can I see this sum?

1 answer

This widget could not be displayed.

Hi!

Since its kind of a report, I think you can find this in the Project / Reports menu. I suggest to check the Time Tracking Report, which summarize the estimated and spent time as well!

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Published yesterday in Marketplace Apps

The 7 hacks of highly successful automation

...there's anything I've learnt from working, it's that people are lazy! No offense to anyone reading this, but it's true and we can all admit it. The easier you make something for someone, the more...

131 views 0 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you