I have stories created on a board that are brought into another board by using the Escalated field. The stories come through fine. But when a subtask is created on the new board, the subtask is not inheriting the "Escalated" field value, and thus not showing up. Does anyone have a solution to this? Escalated is a custom field
The problem was that the sub-tasks were getting created with a status that was precluded from the board. I fixed it by changing the Sub-task workflow so they get created with a status that makes them show up on the current board. Thanks for the idea!
Glad I could point you somewhat in the right direction! :o)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you have access to any scripting add-on? I think you would need to add a post-function to the 'Create' transition for your sub-tasks to copy the Escalated value from the parent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.