Story Points vs Assignee

Hi,

I am talking about a kanban project. I am assigning story points to my issues in kanban project just to know magnitude of work my team has. I am also planning to add estimate to my stories from now on. My current format for says "Time estimates will be displayed in the following format: pretty (e.g. 4 days, 4 hours, 30 minutes)"

My needs:

Primary :1) I want to track number of story points assigned against each assignee. Like I want to see Amit has 50 StoryPoints to work, Ragini has 70 story points to work etc.

Secondary :2) How do I enter (format) the estimate field: Just give a number (what does that number mean) or enter as 1 week, 2day, 3hr (its so long). Please suggest.

I don't care its its any screen, or gadget or board or report but I want to see primary statistic. Please help.

Thank you.

1 answer

@Nic Brough [Adaptavist]; @Jobin Kuruvilla [Go2Group]; @Renjith [Atlassian] Could you please help!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published 2 hours ago in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

13 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you