Show time since issue was created on Structure

Hi,

Is it possible to show the amount of time passed since an issue was created on a Structure, e.g. 1 week, 3 months, etc? I tried using the "Time Spent"column, but it's always empty. When a issue was created, the "Due Date" was usually left empty. Is this why "Time Spent" is empty?

1 answer

1 accepted

1 vote
Answer accepted

Hi Rayne,

You can check how much time has passed since issue creation by using a Formula Column. Specific formula to use would be NOW()-created and the format to select - Duration. Please, let me know if it is what you are looking for.

I must note Time Spent is the accumulation of Work Logged, and only fills when someone is actively logging work on the issue, regardless of value of due date.

Regards,
Egor Tasa

ALM Works

Yes, that's what I was looking for. Thanks!

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Posted in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

3,934 views 11 5
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you