Scrum burn down chart for stories done but not accepted

I have added a status of "Accepted" after my "Done" status and both are considered finished in the workflow. I'm expecting to get credit for a story as soon as a story enters either of these status, but it seems that I'm only getting the points if it reaches "Accepted". How can I configure my workflow to get the points completed when it hits Done?

1 answer

Hi Jared, 

Your board always considers any issues that are in the last column as done.  If you need 2 different statuses to be used for this, you'd need to put them both in the same, last column.  If both statuses are available in the same column you should see two boxes in that column when moving issues, one for each status available, and they should be labeled accordingly.

Eric

Suggest an answer

Log in or Sign up to answer
Community showcase
Asked Thursday in Jira Ops

I'm John Allspaw, Ask Me Anything about incident analysis and postmortems

I'm John Allspaw, co-founder of   Adaptive Capacity Labs, where we help teams use their incidents to learn and improve. We bring research-driven methods and approaches to drive effective inciden...

682 views 6 6
View question

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you