Scrum and Kanban in One Board

For a holistic view of my teams work we use a Kanban board.  However, this board includes other Scrum projects with sprints.  If a task in a Scrum project is in the backlog it doesn't show on our Kanban board (which is how I want it to work).  However, if a task is in a sprint and then gets moved to the backlog it still shows on our Kanban board.  Ideally only items in active sprints would show on our board.  Is there a way to make that happen?

2 answers

1 accepted

3 votes
Accepted answer

You can amend the board filters to meet these needs.

For example, changing the kanban board filter to say "and sprint in opensprints()" would stop most of the non-active issues showing.

This fixed it. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

30 views 2 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you