Hi All
We use the due-date feature a lot.
But sometimes say there are three tasks and all three dependent on each other. When there is a delay in first it causes a ripple effect on 2nd and 3rd.
How can we configure JIRA to automatically update the due-dates for 2nd and 3rd issue?
I am aware of the gantt chart plugin but is there away of doing it natively within jira?
Rahul
One way would be to implement an issue listener that monitors a task for change in due date and then if it detects a change it gets all dependent tasks and updates their due dates.
If you have Script Runner or JJUpin you should be able to quickly add a scripted listener to do that. I'm also assuming that the dependency between the tasks is expressed in some way i.e. issue links.