Scheduling capability

Hi All

We use the due-date feature a lot.

But sometimes say there are three tasks and all three dependent on each other. When there is a delay in first it causes a ripple effect on 2nd and 3rd.

How can we configure JIRA to automatically update the due-dates for 2nd and  3rd issue?

I am aware of the gantt chart plugin but is there away of doing it natively within jira?

Rahul

1 answer

This widget could not be displayed.

One way would be to implement an issue listener that monitors a task for change in due date and then if it detects a change it gets all dependent tasks and updates their due dates.

If you have Script Runner or JJUpin you should be able to quickly add a scripted listener to do that. I'm also assuming that the dependency between the tasks is expressed in some way i.e. issue links.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

172 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you