Scheduling capability

Hi All

We use the due-date feature a lot.

But sometimes say there are three tasks and all three dependent on each other. When there is a delay in first it causes a ripple effect on 2nd and 3rd.

How can we configure JIRA to automatically update the due-dates for 2nd and  3rd issue?

I am aware of the gantt chart plugin but is there away of doing it natively within jira?

Rahul

1 answer

One way would be to implement an issue listener that monitors a task for change in due date and then if it detects a change it gets all dependent tasks and updates their due dates.

If you have Script Runner or JJUpin you should be able to quickly add a scripted listener to do that. I'm also assuming that the dependency between the tasks is expressed in some way i.e. issue links.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

525 views 1 15
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot